OK Guys, drum roll please.... Here's the results from last night. We queued up 1,580 users in a single batch an let her fly. Here's the numbers.
Total Users to Migrate: 1,580
Run Time: 11hrs, 43 Mins
Average Users per hour: 135
Migration completed successfully (1st Pass) - 417
Migratoin Completed, but pending Policy - 1,099
Migration Skipped due to Violation - 64
Projected Failue Rate: 10%
Actual Failure Rate: Less than 5%
Ok, so the real question - Morning after - help desk calls logged: 2